Washington State Department of Transportation
WSDOT NewsSite IndexContact WSDOTWSDOT Home
Traffic & RoadsProjectsBusinessEnvironmentalMaps & Data
Tacoma Narrows Bridge Project

Project Info
•  

Project Home

•  

Bridge - This Week

»  

Building the Bridge

•  

Finance & Schedule

•  

History & More

•  

Just the Bridge Facts

•  

News on the Bridge

•  

Night Construction

•  

Photo Album

•  

Tolls: Good To Go!

•  

Traffic Information

•  

Viewing at Narrows Park

•  

Bridge Opening 2007

   

Construction Cameras
View of East Tower construction from the West Tower

•  Nighttime noise construction information, (253) 620-4440
•  Contact the TNB Office, 1 (877) 762-7769

Contact us

Lisa Murdock
  Olympic Region Communications Manager
  (360) 357-2789
Claudia Cornish
  Media Relations Manager
  (253) 534-4646
Erin Babbo-Hunter
  TNC Public Affairs Manager
  (253) 853-9777
WSDOT Olympic Region
  (360) 357-2600
Contact us and tell us
what you think:
orfeedback@wsdot.wa.gov or
Online Bridge Form

WSDOT
3214 50 Street Court NW, Building D, Suite 302
Gig Harbor, WA 98335

TNC
2110 14th Ave. NW
Gig Harbor, WA 98335


» Unsubscribe

Building the Bridge

Suspension Bridge: Learn more about the Caissons Suspension Bridge: Learn more about the Towers Suspension Bridge: Learn more about Cable Spinning Suspension Bridge: Learn more about the Bridge Deck Suspension Bridge: Learn more about the Anchorage Suspension Bridge

Interactive illustration of a suspension bridge
Hover over the structural elements to learn more

Deck

Building a Suspended Roadway

Piecing together a suspended roadway represents the represents the fifth and final phase of the new Tacoma Narrows Bridge project. The entire deck-lifting process will take four months to complete.

The mile-long roadway is made up of 46 deck sections. The sections, which were built in South Korea, will arrive in The Narrows on three separate deliveries. The first of 16 sections arrived in Puget Sound in early June 2006.

The deck sections that average 120-by-78 feet and weigh 450 tons will be lifted one at a time with “gantry cranes” (special lifting hoists) that straddle the cables. Two different types of gantry cranes will be used to hoist the bridge deck sections into place. On the side spans, the gantries’ lifting mechanisms are winches located on the caissons. In the mid-span area, the gantry cranes lift the sections using strand jacks located on the gantries’ main girders. Each section will be attached to vertical suspender cables, and then connected to the main cables.

The first deck section will be placed in the center span location. The main suspension cables will deflect (sag) 12 feet as a result of the first deck section being lifted into place. This change will cause a rather dramatic change in the cables’ geometry. The weight of the first deck section will shape the cable into a "v" at midspan. It will appear as a “v” until crews install sidespan deck sections to act as counterweights. The remaining 45 blocks will be lifted in an order that, to the casual observer, may appear almost random. That is not the case. Rather, the non-linear order of lifting sections is designed to maintain equal stresses on the bridge’s two towers. The precise lifting sequence ultimately will pull the towers back to a plumb, vertical position.

During tower construction, the bridge builder used large cables to pull the tower tops about two feet toward shore. That was done so that during the deck installation phase, the weight of the sections would pull the towers toward one another and back to a perfectly vertical alignment. The weight of all 46 sections will pull and lower the main cables about 25 feet below its present and non-weighted profile. This stretching process will place the new bridge deck at the same level as the 1950 bridge deck.

As construction gets underway in July 2006, passersby will notice crews simultaneously building the deck out from the east and west anchorages. In the initial assembly of the sections, the deck pieces will be joined temporarily with shear lugs and bolting fixtures. When the majority of deck sections are in place and the cables near their final profile, the crews will weld the deck plates and bolt all other truss sections together.

Like the new towers, the new bridge deck is different from the 1950 span. Instead of a lightweight concrete deck surface, the new deck will be composed of lighter steel plates with beams running lengthwise and crosswise. (Engineers call the surface an “orthotropic” deck.) It’s a type of deck that enables a suspension bridge to perform better under different loads, temperatures, winds and earthquake conditions.

The new bridge deck will have only two expansion joints - one on the east side and one on the west side. Each will allow up to 30 inches of bridge deck movement. That movement can be caused by thermal (temperature) changes, seismic events, wind, and even forces generated by vehicles braking and accelerating on the bridge. That configuration is in contrast to the existing bridge deck, which has large expansion joints at each tower and smaller expansion joints every 120 feet along the length of the deck.

Deck lifting and assembly of all sections is scheduled to be complete in early 2007. Once the deck has been bolted and welded together to form a seamless roadway, the surface will be topped by two inches of asphalt.

Tacoma Narrows Bridge caisson construction
The new bridge deck will be continuous (meaning individual sections will be bolted and welded together to make one piece), with expansion joints located only at the anchorages.
The new deck will be 5,400 feet in total length, 2,800 feet in the main span. The average deck section weighs 450 tons and measures 120 feet long, 78 feet wide and 30 feet deep.
On the new bridge deck, there will be four lanes of traffic, two shoulders, and a 10-foot bicycle/pedestrian path separated by a barrier.
The bridge is designed for a second deck (either road or light rail) to be added in the future.
Tacoma Narrows Bridge caisson construction

See glossary for more bridge engineering terms.


« Back to previous page



  Copyright WSDOT © 2005

    Traffic & Roads | Site Index | Contact WSDOT | WSDOT Business | WSDOT Home