Washington State Department of Transportation
WSDOT NewsSite IndexContact WSDOTWSDOT Home
Traffic & RoadsProjectsBusinessEnvironmentalMaps & Data
Tacoma Narrows Bridge Project

Project Info
•  

Project Home

•  

Bridge - This Week

•  

Building the Bridge

•  

Finance & Schedule

•  

History & More

»  

Just the Bridge Facts

•  

News on the Bridge

•  

Night Construction

•  

Photo Album

•  

Tolls: Good To Go!

•  

Traffic Information

•  

Viewing at Narrows Park

•  

Bridge Opening 2007

   

Construction Cameras
View of East Tower construction from the West Tower

•  Nighttime noise construction information, (253) 620-4440
•  Contact the TNB Office, 1 (877) 762-7769

Contact us

Lisa Murdock
  Olympic Region Communications Manager
  (360) 357-2789
Claudia Cornish
  Media Relations Manager
  (253) 534-4646
Erin Babbo-Hunter
  TNC Public Affairs Manager
  (253) 853-9777
WSDOT Olympic Region
  (360) 357-2600
Contact us and tell us
what you think:
orfeedback@wsdot.wa.gov or
Online Bridge Form

WSDOT
3214 50 Street Court NW, Building D, Suite 302
Gig Harbor, WA 98335

TNC
2110 14th Ave. NW
Gig Harbor, WA 98335


» Unsubscribe


Just the Bridge Facts

At a Glance

Project Scope: 3.4 miles of roadway including new bridge. Boundaries are from Jackson Avenue NW in Tacoma to 36th Street NW in Gig Harbor.
Completion: New bridge in summer 2007
1950 bridge retrofit in spring 2008.
Owner: WSDOT
Contractor: Tacoma Narrows Constructors (Bechtel and Kiewit venture)
Cost: $849 million ($800 million paid by tolls)
Initial Toll: TNB financial plan assumes $3 roundtrip toll in first year; collected in eastbound direction.

New Bridge Vital Statistics

Bridge Length (overall): 5,400 feet
Main Span (tower to tower): 2,800 feet; 69 pairs of suspender hangers per side.
Side Span, East: 1,200 feet; 29 pairs of suspender hangers per side.
Side Span, West: 1,400 feet; 34 pairs of suspender hangers per side
Suspended Roadway (deck panels, barriers, utilities)

53 million pounds
46 deck sections
120-feet long by 78-feet wide by 30-feet high (including hand railing) is average size

Towers: 510 feet tall
8,500 cubic yards concrete (per tower)
2.9 million pounds of reinforcing steel (both)
Caissons (tower foundations, each): 85,000 tons (total weight)
6 million pounds of reinforcing steel
40,500 cubic yards concrete (Tacoma)
37,000 cubic yards concrete (Gig Harbor)
Anchorages (each): 81 million lbs (total weight)
20, 000 cubic yards concrete
1 million pounds reinforcing steel
Cable Diameter (each): 20.5 inches
Each cable contains 19 strands of 464 wires
Individual steel wire is the diameter of a pencil
8,816 steel wires per cable
Structural Steel, Superstructure
(parts of the bridge above water):
35.5 million pounds
Structural Steel,
Suspension System
(cable wire and saddles atop towers):

12 million pounds