Tacoma Narrows Bridge Project

Project Info
•  

Project Home

•  

Bridge - This Week

•  

Building the Bridge

»  

Finances & Schedule

•  

History & More

•  

Just the Bridge Facts

•  

News on the Bridge

•  

Night Construction

•  

Photo Album

•  

Tolls: Good To Go!

•  

Traffic Information

•  

Viewing at Narrows Park

•  

Bridge Opening 2007

   

Construction Cameras
View of East Tower construction from the West Tower

•  Nighttime noise construction information, (253) 620-4440
•  Contact the TNB Office, 1 (877) 762-7769

Contact us

Lisa Murdock
  Olympic Region Communications Manager
  (360) 357-2789
Claudia Cornish
  Media Relations Manager
  (253) 534-4646
Erin Babbo-Hunter
  TNC Public Affairs Manager
  (253) 853-9777
WSDOT Olympic Region
  (360) 357-2600
Contact us and tell us
what you think:
orfeedback@wsdot.wa.gov or
Online Bridge Form

WSDOT
3214 50 Street Court NW, Building D, Suite 302
Gig Harbor, WA 98335

TNC
2110 14th Ave. NW
Gig Harbor, WA 98335


» Unsubscribe


Finances & Schedule

In the nearly four years since the Washington State Department of Transportation began construction of the new Tacoma Narrows Bridge, the overall project is more than 80 percent complete. The $849 million project consists of constructing a parallel suspension bridge, improving 2.4 miles of roadway on State Route 16, and retrofitting the adjacent 1950 bridge. The new bridge will open to traffic in summer 2007 with both bridges opening in their final form by spring 2008. When the project is fully completed, the existing bridge will carry westbound SR 16 traffic (to the Peninsula) while the new bridge will take vehicles eastbound on the corridor (toward Tacoma).

2002  
September: WSDOT and Tacoma Narrows Constructors start new Narrows Bridge design work.
October: Groundbreaking ceremony held October 5.
   
2003  
January: Roadway construction begins.
March: Cutting edge # 1 (base of foundation) leaves Seattle for Tacoma.
April: Cutting edge #2 (base of foundation) leaves Seattle for Tacoma.
July/August: Caissons (foundations) towed from Port of Tacoma to the Narrows.
September: New 24th Street NW underpass opens to traffic.
October: Westbound State Route 16 ramps at 24th St NW open to traffic;
east anchorage fully excavated; related concrete pours begin.
December: Gig Harbor caisson reaches seabed: first touch down.
   
2004  
January: Tacoma caisson reaches seabed: second touch down; west anchorage fully excavated.
February: Deck and suspension cable fabrication begin in Korea; west anchorage concrete pours begin.
March: Air domes cut out of both caissons; seabed dredging begins.
May/June: Caissons reach full height and are sealed.
July: Tower construction begins.
   
2005  
April: East anchorage, including placement of splay saddles, is completed.
May: West anchorage, including placement of splay saddles, is completed.
June: New concrete bridge towers are topped off at 504 feet;
towers reach final elevation at 510 feet with installment of saddles (steel castings).
August: Construction begins on suspended walkways for cable-spinning.
October: Cable spinning officially begins: first pencil-sized cable wire is pulled across the Narrows.
   
2006  
January: South main cable spinning completed.
April: North main cable spinning completed.
June: Pre-assembled deck sections arrive by ship in Narrows.
August: Deck section assembly begins.
   
2007  
Summer: New bridge is complete and opens to traffic in temporary lane configuration.
   
2008  
Spring: 1950 bridge retrofit is complete; new bridge carries eastbound traffic and old bridge carries westbound traffic.


Project Progress To Date (Percent Complete)

Overall

   

81.0

Construction

   

79.6

Design

 

99.9

» Monthly Project Status Reports
» Night Construction Work

Financial Information

  • Fixed Price Summary  The fixed price is the cost of constructing the new bridge and related project work. The project is a "fixed price" project.
  • Capital Funds Summary  This describes the sources of revenue and uses of the funds required for the entire Tacoma Narrows Bridge Project and related costs repaid by tolls.
  • Design/Build Agreement Summary  Brief description of the design-build style of construction for the Tacoma Narrows Bridge Project.